A data centre expansion in Cambridge, Ontario, anchored by the AI startup Cohere, has triggered an urgent power capacity crisis that is already raising electricity bills for local residents and businesses, according to an investigation by the Toronto Star.

In late 2024, the Independent Electricity System Operator (IESO), which manages Ontario's power grid, sent a letter to local utility GrandBridge Energy and transmission operator Hydro One that used the word "urgent" nine times. The letter warned that "urgent" growth in electricity demand had created "urgent" needs requiring "urgent" investments to increase power capacity to the Cambridge region, the Star reported. The IESO directed the utilities to "proceed immediately" with projects to address the shortfall.

While the letter did not single out any specific power user, it cited "large new data centre customers" as the first reason for the load growth. The Star's investigation, which used artificial intelligence to search more than 20,000 regulatory filings at the Ontario Energy Board (OEB), found that utilities across Ontario are facing critical power capacity challenges driven or exacerbated by the data centre boom.

Nowhere is the tension between Canada's AI ambitions and local costs more evident than in Cambridge, where the needs of Cohere — a Toronto AI startup that recently received a $1.6 billion direct equity investment from the federal government and a $240 million pledge for computing access — helped set off a rapid and expensive scramble for solutions, the Star reported.

According to the Star, GrandBridge Energy filed an application with the OEB last year describing a plan to bring more power online quickly. The IESO's letter recommended GrandBridge immediately start work on a new transformer station costing $40 million, and told Hydro One to begin upgrading circuits and constructing other transmission infrastructure at a cost of up to $390 million. These upgrades would remove a limitation restricting power capacity at Cambridge's three existing transformer stations.

"Without immediate action," GrandBridge warned in its application, the shortfall could create "unacceptable" outcomes, including difficulty managing outages that raised the possibility of extended blackouts.

Ali Hooshyar, an energy systems expert at the University of Toronto, told the Star that the language surrounding the new transformer station is unusual. "Usually, things do not happen so urgently," Hooshyar said. "A new transformer is not something that you go and buy off the shelf from Walmart."

Even with immediate action, the new transformer station would not be ready until 2028. Forecasts showed Cambridge's transformer stations nearing their capacity limits this year, and in some scenarios exceeding those limits by the summer of 2027. To bridge the gap, GrandBridge applied to the OEB for permission to launch a "Gridshare" program that would pay businesses and institutions to reduce demand at peak periods, budgeting around $3 million over three years.

Board staff questioned why the capacity gap existed and why the utility had not built the new transformer station sooner. GrandBridge told the board it had known for several years that a new station would eventually be needed — it acquired land for the future station in 2018 — but electricity demand was growing at a gentle pace. Planning for the new station "as an urgent need" began in late 2024, "after a significant growth in new load arose," GrandBridge wrote.

Data filed by the utility shows demand across the three stations serving Cambridge was forecast to jump by more than 20 megawatts (MW) in 2025, and more than 65 MW in 2026 — an increase of more than a quarter of the stations' previous power load, compared to roughly 2 per cent growth in prior years.

GrandBridge blamed the rise on "new data centres, commercial developments along major highways, urban densification, residential growth, and transportation electrification." The utility would not say how many data centre customers it has or identify their power demands, but it did answer a question about how many new large customers it has connected in recent years: only one, a customer that connected in 2025.

According to the Star, one of the IESO's system impact assessments — posted publicly — reveals that GrandBridge sought permission from the IESO to link an 80 MW data centre to its Cambridge transformer stations. The client intended to begin drawing power from the grid in 2025, initially consuming 16 MW that year and eventually reaching full capacity in the current year. At peak operation, the facility's electricity consumption would be comparable to that of roughly 20,000 households. The data centre's identity is not disclosed in the document, but Cambridge planning staff told the Star that the city has only one large data centre in operation — the one in the northwest corner of the city, where Cohere is the anchor tenant.

City staff approved a major expansion involving at least four U.S. companies: Coreweave, which leases AI computing infrastructure and has a partnership with Cohere, along with Related Digital, Ascent, and TowerBrook Capital Partners, who are referred to as joint developers. The facility also has at least one additional tenant that was there before the expansion.

Multiple experts told the Star that all available evidence points to the data centre as the primary culprit for Cambridge's urgent capacity problems. Mark Winfield, a professor of environmental and urban change at York University who has worked in energy policy for decades, said that residential and commercial growth are "highly unlikely" to cause such a large and sudden increase in demand.

Winfield told the Star that Cambridge's saga raises "layers upon layers upon layers of questions" about sustainability, sovereignty, and spending to support the infrastructure necessary for data centres. "The main one," he said, "is who pays — and is that fair?"

Local residents and businesses are already footing higher bills for the sudden surge in power demand, the Star reported, even though both federal and provincial officials had promised that data centres would not pass energy expenses on to ratepayers.

Kyle Lastovica, who speaks for Cohere, informed the Star that the firm backs the government's stance that data centres ought to cover their own costs. Data centres "should create lasting economic benefits, pay for their own energy rather than shifting electricity costs onto Canadians, minimize environmental impacts, and operate with transparency," Lastovica said. He added that Cohere does not own or operate the data centre in Cambridge, though the Star confirmed Cohere is a tenant there.

Provincial authorities, local utilities and facility operators, citing confidentiality concerns, have withheld information about where data centres are being built, who owns, operates, and uses them, and how much power they will draw from the existing power grid, the Star reported. Umar Waqas, GrandBridge Energy's vice president of grid modernization, told the Star in a statement that "protecting our customers' privacy and confidential business information is an important part of our responsibility." Waqas did say that data centres currently represent around 12 per cent of total demand in Cambridge, up from approximately 1 per cent in prior years.

For university students in Ontario and across Canada, the story highlights how the push for AI leadership — backed by billions in public investment — can have direct, local costs. Students already grappling with rising living expenses may see further increases in electricity bills, and the infrastructure demands of data centres raise questions about how public money is being spent and who ultimately bears the burden.