Cornell University has released a sweeping 40-year master plan for its Ithaca campus utilities that will fundamentally change how more than 150 buildings are heated and powered, according to the Cornell Chronicle. The Utilities Reliability and Energy Transition (UR&ET) Master Plan calls for a $1.1 billion capital investment over four decades, combining practical upgrades with emerging technologies to eliminate fossil fuel use and comply with New York state's Climate Leadership and Community Protection Act (CLCPA).
For students, the plan means a campus that will eventually run without routine natural gas or fuel oil, with heating supplied by stored geothermal energy rather than a central power plant. The transition will also create hands-on learning opportunities: the Facilities and Campus Services (FCS) team is working with master of engineering students and student groups to incorporate borehole drilling and system installation into coursework.
The plan begins with a $93 million investment over the next five years, including expanded cooling capacity, building efficiency improvements, and an accelerated conversion from steam to hot water heat — a process that involves replacing 110-year-old steam pipes. A key pilot project, the Borehole Thermal Energy System (BTES), will drill boreholes up to 850 feet deep to store waste heat in summer for redistribution to buildings in winter. Eventually, the system could comprise 1,800 boreholes across campus, paired with heat pumps and solar thermal technology, replacing the Combined Heat and Power Plant that currently runs on natural gas with fuel oil backup.
Cole Tucker, associate vice president of Energy and Sustainability in FCS, told the Chronicle that maintaining the current system with only necessary upgrades over 40 years would still cost about 90% of the new plan's total, while leaving the university out of compliance with state law. "Business as usual is not a zero-cost option," Tucker said. "We've got aging infrastructure and demand growth that we have to stay after."
The BTES pilot is expected to begin in spring 2027 with up to five test bores. Stacey Edwards, the UR&ET program manager, said the goal is to collect enough data to build and tune a model before scaling up. "There are some pretty exciting, interesting steps along the way," she said. The first fully functional BTES will be on East Campus, storing summer waste heat from the power plant for winter delivery to the College of Veterinary Medicine.
Edwards noted that at a pace of one borehole per day, Cornell could be drilling for four straight years. "This is not a trivial exercise ahead," Tucker added.
The plan sidelines the Earth Source Heat geothermal project, which requires much deeper and more complex drilling. While engineers found temperatures at the Cornell University Borehole Observatory to be hot enough, more drilling is needed to determine viability. The master plan keeps that technology open as a future option.
Tucker's team researched and modeled more than a dozen scenarios, engaging stakeholders across the campus and Ithaca communities, peer institutions, industry partners, and state agencies. Consultants from Jacobs Engineering were retained, and the team ran multiple feasibility studies. "We couldn't risk having the consultants give us a bright and shiny plan that actually didn't work for us," Edwards said.
The Cornell Board of Trustees Buildings and Properties and Finance Committees voted unanimously in support of the plan on October 15. Tucker called the team "the highest performing team that I've ever been on in my life" and said they created "something amazing that we hope will last another 100 years."